How to set out a building plan on the ground

Architects building plan

Before contractors can begin a construction project, they first need to lay the building plans on the ground. This is the process of making the outline of the structure, to the exact dimensions, on the location of where it will be built. The building plan will show contractors where to dig and lay the foundations for the building.

The building plan is often marked by pegs and string, but some contractors like to use white paint on the ground. Pegs are hammered into the ground and attached by a string along the centreline of walls. Contractors need to make sure that the pegs and string follow the architect’s drawings perfectly. 

Steps to laying a building plan on the ground

  1. Clear any long grass and rocks from the construction site where the building will stand. Remove any debris and skim off the topsoil. This will make the marking process easier and clearer.
  2. From the architect’s drawing, start by hammering a peg into the ground at one of the corners of the building (call it point A). Measure the distance of the wall, using the architectural plan as a reference, and place another peg in the ground where the next corner of the wall will be (point B). 
  3. Place a peg two metres away from point A and point B and connect these two pegs with the string. These pegs (call them A1 and B1) will help contractors excavate the foundations later without having to move the string or corner pegs.
  4. Repeat this process of placing pegs at all the corners of the walls (points C and D) and placing additional pegs two metres away. Attach all the outer pegs with string. Each corner point should have two pegs (corner A will have peg A1 joining B1 and A2 joining D2). Where the strings cross will mark the exact corner of the walls.
  5. To make sure that the corners are 90°, the centre points of the rooms needs to be calculated. Measure the distance between opposite corners (point A and point C) on the architect’s drawings. Make sure that the real distance between the pegs at point A and point C match the distance on the drawing. You may have to move the pegs a bit to make these diagonal measurements are exact.
  6. Where the diagonal strings cross is the centre point of the room. The opposing walls (AB and CD or AD and BC) should be the same distance from this centre point.
  7. Once all the strings are laid, the contractors can start excavating the foundations. The extra two metres of string at each corner will allow the contractors to dig the foundations without having to excavate any corner pegs. The strings will be used as a guide for the centreline of the walls.
  8. Some contractors like to spray white spray paint on the ground or use lime to demarcate the path of the wall underneath the strings. This just helps to dig the foundation more accurately.

___

LafargeHolcim is a leading building materials and solutions company that has been operating in international markets for decades. We produce cement and aggregates for construction projects, ranging from small affordable housing developments to large-scale infrastructure projects such as high-rise buildings, dams and bridges. 

___

LafargeHolcim Tanzania has been supplying the country and neighbouring countries with our world-class Tembo cement brand for over 30 years. Our head office and fully-integrated plant are located in Mbeya, Southwest Tanzania.

___

At LafargeHolcim Tanzania, we believe customers come first. We listen to your specific requirements to supply and develop the best solutions for your needs. As the new leader in building materials, you can also rely on our cutting-edge research and development capabilities that have resulted in the finest materials for your construction projects, whether large or small.

___

Follow us on Facebook, Twitter, LinkedIn and Pinterest for the best tips on construction, handy projects and the latest industry news. See our Instagram channel for more insights into our products.

Synthetic fibres can increase the durability of concrete

Contractors sometimes add synthetic fibres to their concrete mix. These fibres of man-made polymers are specifically engineered to withstand the long-term alkaline environment within a concrete mix. They are used to minimise cracking, lower the permeability of the concrete and increase the strength of the structure. They act as a secondary reinforcement element; the primary …

The eight types of construction company

There are many different types of construction company. Not all contractors specialise in the same fields and not all companies do the same construction work. Depending on the type of work they do, construction companies can be classified into the following eight types: 1. General contractors A general contractor provides all of the labour, equipment, …

How to fix common concrete slab problems

When working with concrete, contractors may encounter a few different problems. The following issues can sometimes occur when pouring concrete slabs. While some aspects of working with concrete slabs have changed over the years, many issues have not. Here are three common problems that come with pouring concrete slabs, and their possible solutions. 1) Excessive …

How to prevent dampness in a building

Dampness in a building may occur due to faulty construction, the use of poor-quality building materials or bad architectural design. Dampness affects the lifespan of a building or structure, but it also creates unhygienic conditions. Mold and fungi love to grow in damp conditions, so it is best to fix any signs of wet concrete …

The importance of having a schedule for a construction project

Construction projects are delicate operations that need to run on time in order to stay within the allocated budget. As soon as a project is delayed, it costs the contractors and building owners more money. Having a strict schedule is important as it keeps the project on time and allows all workers to know when …

How to prepare a concrete surface for a topping

Sometimes concrete surfaces are given a decorative topping that adds further protection and durability to a floor or carpark. The underlying concrete will need to be prepared properly before any topping is laid on top. This will ensure that a good bond is formed between the two materials and that no cracks or chips will …